A.
Project Description
|
Item |
Description |
|
1. Name of Project |
Muko Muko Kanan Irrigation Sub-Project |
|
2. Location |
(1)
General Layout is shown in Figure A-1.
(2)
Project Location and Administration
·
Province : Bengkulu
·
District : Bengkulu
Utara
·
Sub-districts : Muko Muko
Utara and Pwk. Lubuk Pinang
350 km northwest of Bengkulu
town |
|
3. Objective |
(1)
To enhance rice production through water resources development
(2)
To increase the income of inhabitants in and around the project
area
(3)
To raise the farmers living standard
(4)
To increase employment opportunity in the area
(5)
To contribute to the development of the rural socio-economic
conditions |
|
4. Type of Development |
(1)
Improvement of existing main irrigation canal
(2)
New construction of irrigation and drainage systems
(Intake weir and part of main canal
2.252 km: already constructed) |
|
5. Irrigation Development Area |
(1)
Whole project area : 4,919 ha
(2)
Target area under PTSL-II : 3,957 ha
The peat soil area lying in the downstream
area 962 ha is not implemented at the present time. |
|
6. Water Supply and Water Requirement |
(1)
Water source: Manjuto River
(2)
Available supply of water: as shown in Table A-1
(3)
Irrigation water requirement: as shown in Table A-2
(4)
Design unit water requirement: 1.63 l/sec/ha |
B.
Contribution of the Project to Water Resources/Irrigation
Development
|
Item |
Description |
|
1. Necessity of the project |
Entering the 1990s the self-sufficiency of
rice in Indonesia is facing a crisis. Rice production is quite abnormal
and irregular compared with the 1980s. The average unit yield of rice
stands stationary in the 1990s. The expansion of irrigation area lost
momentum in the 1990s, and the rice import resumed from 1994. Under
such situation, the Government has adopted a policy of food security and
sustenance of self-sufficiency in rice production.
The crop intensity of paddy fields in
Indonesia is as low as 119% that indicates a possibility to expand the
harvested area and thereby to increase the rice production through the
irrigation development. In 1999, there was about 2.1 million ha of
rain-fed paddy fields and 1.17 million ha of upland paddy fields in
Indonesia, for which the irrigated agriculture can be efficiently
introduced without major problems such as transmigration, large-scale
land development, social infrastructures, etc.
In order to promote the food security and
sustenance of self-sufficiency in rice production, the government is
keen to implement the irrigation development being effective for rice
production, quick yielding and cost effective
|
|
2. Beneficiary Area |
The socio-economic condition of the people in
the project area is at the subsistence level due to the limited income
from agricultural activities. The basic development constraint is the
lack of irrigation water.
The Muko Muko Kanan sub-project is a part of
Muko Muko Irrigation Project, consisting of Muko Muko Kanan and Muko
Muko Kiri schemes. The intake weir was constructed in 1989, and
irrigation facilitates for Muko Muko Kiri scheme were also completed.
Irrigation supply for Muko Muko Kiri scheme was made for an area of
6,203 ha. The main canal in its two reaches of Muko Muko Kanan was
constructed in 1999 and 2000, but not used. The remaining irrigation
facilities will be constructed under PTSL-II.
With the project implementation, the
principal benefit of the project is as follows:
·
Increase of unit yield of crop
by changing from rain-fed agricultural land to irrigated land |
C. Project Area
|
1. Water resources |
The irrigation water is taken from the Manjuto river at the existing
Manjuto intake weir, having a catchment area of 440 km2 at
the intake weir site.
The average discharge, the maximum, and the minimum (10 days basis) at
the intake weir site are estimated to be 30.0 m3/sec, 66.7 m3/sec
and 9.1 m3/sec, respectively.
The Muko Muko Kanan iirrigation sub-project is a part of Muko Muko
Irrigation Project, which consists of Muko Muko Kanan scheme and Muko
Muko Kiri scheme. The Muko Muko Kiri Scheme has been constructed and
serving for an irrigation area of 6,203 ha from the Manjuto intake
weir.
The overall water balance simulation between the Manjuto river flows and
irriagtion water requirements of Muko Muko Irrigation Project shows that
the river discharge is sufficient for the Muko Muko Kiri Scheme of 6,203
ha and the Muko Muko Kanan Sub-project area of 4,919 ha with a cropping
pattern of paddy-paddy-palawija (annual cropping intensity of 250 %).
|
|
2. Land use |
The present land use is as shown below.
·
Rain-fed
paddy field : 1,475 ha
·
Upland : 1,970 ha
·
Bush/Forest : 512 ha
Tertiary system for rainfed paddy fields
1,475 ha is required.
Land development inclusive of tertiary system
for upland 1,970 ha and bush/forest areas 512 ha is needed.
The development area of Muko Muko Kanan
sub-project in its original design is 4,919 ha, which includes the
downstream peat soil area of 962 ha. The drainage canals have been
constructed in the peat soil area, which stands in the process of
settlement. Therefore, the irrigation development of such area is
postponed and the area is excluded from the scope of Muko Muko Kana
sub-project work under PTSL-II. |
|
3. Institutional setting-up |
There is no water
users association in Muko Muko Kanan sub-project area because most of
the sub-project area is in the rainfed condition.
The water management including O&M of Manjuto intake weir need to be
carried out as the whole Muko Muko project area, therefore sufficient
coordination is required between the existing Kuko Muko Kiri area and
Muko Muko Kanan area. |
|
4. Environmental issues |
All necessary land
acquisition for the construction work has been carried out under the
previous stage of Muko Muko Kanan sub-project. Therefore, no mitigation
measure for land compensation is required.
Present land use
consists predominantly of rainfed area and horticulture areas with small
areas of bush and forest. Areas to be implemented is already mostly
managed agricultural land. The works will therefore not result in
significant change in the natural environment.
There is no major
environmental negative impact in the sub-project area. |
D.
Project Scope
|
|
Item |
Scope of Work |
|
1. |
Main Irrigation Canal System |
|
|
|
(1) Rehabilitation of existing main
irrigation canal |
2.55 km |
|
|
(2) Construction of main irrigation canal
|
19.80 km |
|
|
(3) Construction of secondary irrigation
canals |
|
|
|
Silaut secondary canal |
2.50 km |
|
|
Serik secondary canal |
4.46 km |
|
|
Sumber secondary canal |
2.08 km |
|
|
Tanjung Alai secondary canal |
2.94 km |
|
|
Dusun Baru secondary canal |
0.96 km |
|
|
Curup secondary canal |
0.53 km |
|
|
Sub-secondary canals (6 canals) |
6.90 km |
|
|
(4) Construction of irrigation canal related
structures |
|
|
|
Off-take/division structure |
39 nos. |
|
|
Measuring structure |
2 nos. |
|
|
Road Culvert |
2 nos. |
|
|
Bridge |
- nos. |
|
|
Aqueduct |
2 nos. |
|
|
Cross drain |
42 nos. |
|
|
Drop |
2 nos. |
|
|
Side spillway |
- nos. |
|
|
Over chute |
2 nos. |
|
|
Foot bridge |
20 nos. |
|
2. |
Drainage Canal System |
|
|
|
(1) Rehabilitation of main drainage canal |
- km |
|
|
(2) Construction of main drainage canal |
15.26 km |
|
|
(3) Construction of drainage canal related
structures |
|
|
|
Gabion Drop |
2 nos. |
|
|
Culvert |
- nos. |
|
|
Drain inlet |
- nos. |
|
3. |
On-farm System |
|
|
|
(1) Tertiary canal system |
1,475 ha |
|
|
(2) Land development including tertiary
system |
2,482 ha |
E.
Implementation Schedule
The implementation schedule of the project is
presented as follows:


(1)
The civil work of the main irrigation and drainage systems will
commence in December 2004 and be completed in May 2007 for a construction
period of 30 months.
(2)
The civil work of the tertiary system and land development will
commence in March 2005 and be completed in February 2007 for a construction
period of 24 months.
F.
Organization and Management Structure
|
Item |
Description |
|
1. Executing Agency |
Directorate General of Water Resources,
Ministry of Settlement and Regional Infrastructure |
|
2. Implementation Management |
Implementation of Muko Muko Kanan Irrigation
Sub-project is managed by the sub-project manager of Muko Muko Kanan
Irrigation Sub-project. |
|
3. Monitoring and Management |
·
At the sub-project level, the
sub-project manager will monitor and control physical and financial
progress of the project work under the guidance of Bengkulu Irrigation
and Swamp Project Manager and the Chief of Provincial Water Resources
Services.
·
At the central level,
Directorate of Water Resources in Western Region (DWRW) is responsible
for monitoring the progress of the project. DWRW will report the
progress to Directorate of Technical Guidance (DTG).
·
DTG will compile the
information together with other sub-projects information to prepare the
progress report to JBIC.
The organization and management structure of
project implementation is as per attached in Figure G-1. |
|
4. Payment Procedure and Monitoring of
Financial Progress |
·
Direct payment is applied to
the civil work contractors.
·
Any payment will be processed
with the confirmation of the contents of invoices by the PTSL-II
consultant.
The flow chart of payment and monitoring
procedure for financial progress is as per attached in Figure G-2.
|
II. Organization of Operation and Maintenance
Appropriate operation and maintenance activities
by Water Users’ Associations will be incorporated in O&M of the project
through the formation and empowerment of the WUAs on the basis of the
Government Regulation of Irrigation Turnover (PKPI). |
|
|